closure

EXTENDED LANE CLOSURE SCHEDULED ON ROUTE 220 IN ROANOKE COUNTY NEXT WEEK - Drivers of Route 220 northbound should plan for delays

SALEM – As part of the ongoing construction to replace the bridge over Back Creek on Route 220, an extended lane closure has been scheduled for next week. The bridge is near the intersection of Route 657 (Crowell Gap Road and Winter Drive).  Beginning Monday, October 8 at 9 a.m., the right northbound lane of Route 220 and the crossover at Crowell Gap Road will be closed until Wednesday, October 10 at 5 p.m. to pave a segment of the roadway that will connect to the new bridge. Drivers traveling on Route 220 northbound into Roanoke should expect significant delays on Route 220 during this time and are encouraged to plan their travel accordingly. The bridge replacement is expected to be complete in spring 2020. For updates on this project and other traffic impacts and lane closure, visit www.511Virginia.org .




closure

TRAFFIC ALERT: ROUTE 220 LANE CLOSURES WILL HEAVILY IMPACT TRAFFIC TONIGHT THROUGH NEXT WEEK IN FRANKLIN AND ROANOKE COUNTIES - Drivers should plan ahead and expect delays

SALEM – The recent flooding and heavy rainfall has resulted in several slope and shoulder failures along Route 220 in Roanoke and Franklin Counties. During the next week, crews will be working to repair the damage and commuters and travelers will be impacted. Route 220 Southbound between Buck Mountain Road and Yellow Mountain Road in Roanoke County The right lane of southbound Route 220 is closed due to a slope failure on the right shoulder of the road between Buck Mountain and Yellow Mountain Road in Roanoke County.  High water from the heavy rains caused a rock slide that impacted the shoulder of the roadway. The weight caused the shoulder to collapse resulting in the road being pushed out and giving way. The right lane closure will remain in place through Monday evening, weather permitting. Crews are developing a plan to repair the pipe and plan to begin work over the weekend.   Route 220 Southbound at Franklin County Line The left lane of southbound Route 220 has been closed due to a slope failure in the median just south of the Franklin County line. VDOT crews have been working to determine how a pipe under the road has failed and how to proceed with repairs. At this time, the ground continues to settle and move, therefore, the lane will remain closed through the weekend and into Monday . The lane closure is located approximately one mile prior to the Roanoke County and Franklin County line and just north of the intersection with Route 613 (Naff Road).  Route 220 Shoulder Repairs There will be alternating right and left lane closures on southbound and northbound Route 220 next week, weather permitting, to repair shoulders that have been damaged by the heavy rainfall. Drivers using Route 220 southbound and northbound should plan ahead for significant delays during this time until repairs can be made and lane closures are removed. Drivers should plan ahead accordingly. For updates on this lane closure, visit www.511Virginia.org .




closure

CLOSURE OF EXIT 143 AT I-81 AND I-581 DUE TO CRASH TO IMPACT MORNING COMMUTE - Drivers will need to seek alternate routes and allow for extra travel time this morning

SALEM – A crash involving a tractor-trailer has closed exit 143 on I-81 this morning. Access to I-81 from I-581 and access to I-581 from I-81 has been impacted and drivers will need to seek alternate routes during the morning commute. I-81 southbound to exit 143 with access to I-581 southbound is closed. Travelers on southbound I-81 requiring access to I-581 will need to use Route 11 to Peters Creek Road or use Route 460 at exit 150 to return to I-581 or to access the downtown Roanoke area. I-581 northbound to I-81 southbound is closed. Travelers on I-581 from Roanoke heading to Salem using I-81 will need to use Peters Creek Road or other side roads for access back to I-81 at exit 141. In addition, drivers traveling on I-81 northbound and from I-581 to access northbound I-81 should expect delays and heavy congestion. The right lane of I-81 northbound at exit 143 is also closed. Drivers should expect delays in this area through at least 8 a.m. and further delays are possible through the morning.





closure

Route 7 Lane Shifts and Side Street Closures in Vienna and Great Falls




closure

Route 7 Corridor Improvements in Fairfax County Lane Closures May 11-15




closure

I-66 Eastbound between Groveton Road and Sudley Road in Manassas Overnight Traffic Stoppages and Triple Lane Closure May 11




closure

I-66 Eastbound Ramp to Route 28 Northbound in Centreville Overnight Closures May 10 - June 14




closure

I-66 Eastbound and Westbound between Sudley Road in Manassas and Route 29 in Centreville Overnight Traffic Stoppages and Lane Closures May 8-10




closure

I-66 Outside the Beltway Lane Closures and Traffic Changes May 10-16




closure

I-66 Outside the Beltway Lane Closures and Traffic Changes May 3-9




closure

I-66 Eastbound Lane Closure between Lee Highway/Washington Boulevard (Exit 69) and Patrick Henry Drive in Arlington May 8-10





closure

OVERNIGHT RAMP AND LANE CLOSURES AT NORTHBOUND I-81 EXIT 220 IN AUGUSTA COUNTY OCTOBER 21-25

The on-ramp and off-ramp between northbound Interstate 81 and Route 262 (Woodrow Wilson Parkway) at exit 220 in Augusta County are scheduled for overnight closures and detours during the week of October 21-25, 2018. A northbound I-81 right-lane closure will also be in place during this time period. These traffic restrictions allow milling and paving of existing ramps, and an extension of the acceleration lane from Route 262 to northbound I-81.




closure

Fracking disclosure tested by recent spill in Pennsylvania

Despite leading the charge for voluntary disclosure of fracking chemicals, Chesapeake Energy is now resisting revealing what was spilled during a blowout in Pen




closure

Corporate carbon disclosure can boost share prices

A new study shows that share prices increase slightly after a carbon disclosure is made.



  • Sustainable Business Practices

closure

KDM Steel Starts to Manufacture Freestanding Enclosure with Window for the European Market

KDM Steel today began manufacturing freestanding electrical enclosures with windows.




closure

Furr's Fresh Buffet® Announces Temporary Closure of All Restaurants in Response to COVID-19




closure

Prominent Florida Foreclosure Defense Firm Oppenheim Law Announces Deferred Payment Plan for U.S. Government Employees Affected by Historic Government Shutdown

Fort Lauderdale Foreclosure Defense Attorneys look to ease the government employees affected by the current shutdown by helping them with their foreclosure and housing needs, and deferring payment for such services until they return to work.




closure

Temporary Road Closure - Upper Coomera

Streets affected: Days Road (lane closure with traffic control – expect delays) between Williamson Road and Abraham Road

Region:

Category:

Date: 
Thursday, May 7, 2020 - 16:30 to Thursday, May 21, 2020 - 03:00
planned: 
1
Read more: 

Also affected: Williamson Road (lane closure with traffic control – expect delays) between Billinghurst Crescent and Days Road

Start date: 7 May 2020

End date: 20 May 2020

Duration: 6:30am – 5pm

Reason: Bus bay works




closure

Temporary Road Closure - Bundall

Streets affected: Slatyer Avenue (lane closure with traffic control – expect delays) between Ponciana Crescent and Richmond Avenue

Region:

Category:

Date: 
Thursday, May 7, 2020 - 19:00 to Monday, June 8, 2020 - 00:30
planned: 
1
Read more: 

Also affected: Racecourse Drive (lane closure with traffic control – expect delays) between Slatyer Avenue and Mentone Avenue

Start date: 7 May 2020

End date: 7 June 2020

Duration: 9am – 2:30pm

Reason: To facilitate installation of new signal footing and pole




closure

Temporary Road Closure - Main Beach

Streets affected: Breaker Street (full road closure local traffic access only) between Cronin Avenue and Tedder Avenue

Region:

Category:

Date: 
Monday, May 11, 2020 - 16:30 to Sunday, May 31, 2020 - 04:30
planned: 
1
Read more: 

Also affected: Tedder Avenue (full road closure local traffic access only) between Cronin Avenue and Gold Coast Highway

Start date: 11 May 2020

End date: 30 May 2020

Duration: 6:30am – 6:30pm

Reason: To facilitate road profiling and wearing course layering




closure

Temporary Road Closure - Surfers Paradise

Streets affected: Via Roma (lane closure with traffic control – expect delays) between Isle of Capri Bridge and Verona Avenue

Region:

Category:

Date: 
Wednesday, May 20, 2020 - 17:00 to Thursday, May 21, 2020 - 01:00
planned: 
1
Read more: 

Also affected: Amalfi Drive and Brindisi Avenue

Start date: 20 May 2020

End date: 20 May 2020

Duration: 7am – 3pm

Reason: ENERGEX works - to facilitate pole replacement for the Isle of Capri Decongestion Project




closure

Unplanned Temporary Road Closure - Arundel

Streets Affected: Captain Cook Drive (half road closure with traffic control - expect delays) between Captain Cook Close and Logistics Place

Start date: 8 May 2020

End date: 8 May 2020

Duration: 9am - 3pm

Reason: Emergency repair works on a 300mm recycled water main along Captain Cook Drive

Region:

Category:

Date: 
Friday, May 8, 2020 - 19:00 to Saturday, May 9, 2020 - 01:00
planned: 
0




closure

Temporary Road Closure - Surfers Paradise

Streets affected: Norfolk Avenue (half road closure with traffic control – expect delays) between Ferny Avenue and River Drive

Region:

Category:

Date: 
Thursday, May 7, 2020 - 17:00 to Saturday, May 30, 2020 - 03:00
planned: 
1
Read more: 

Also affected: Oak Avenue, Ferny Avenue and Pine Avenue

Start date: 7 May 2020

End date: 15 May 2020   (* verge/footpath closed until 29 May 2020)

Duration: 7am – 5pm

Reason: To facilitate restoration works and final water main replacement and connection




closure

Temporary Road Closure - Broadbeach Waters

Streets affected: Rudd Street (full road closure local traffic access only) between Rio Vista Boulevard and Bermuda Street

Region:

Category:

Date: 
Monday, May 25, 2020 - 05:00 to Wednesday, June 10, 2020 - 15:00
planned: 
1
Read more: 

Also affected: Rio Vista Boulevard (full road closure local traffic access only) between T E Peters Drive and Reef Court

Start date: 24 May 2020

End date: 10 June 2020

Duration: 7pm – 5am

Reason: To facilitate profiling of the road followed by wearing course layer to the roadway




closure

Temporary Road Closure - Stapylton

Streets affected: Quarry Road (half road closure with traffic control – expect delays) between Stapylton Jacobs Well Road and Rossmanns Road

Region:

Category:

Date: 
Tuesday, May 26, 2020 - 04:00 to Wednesday, June 10, 2020 - 16:00
planned: 
1
Read more: 

Also affected: Angel Road

Start date: 25 May 2020

End date: 10 June 2020

Duration: 6pm – 6am

Reason: Road profiling and asphalt works




closure

Temporary Road Closure - Pacific Pines

Streets affected: Pacific Pines Boulevard (lane closure with traffic control – expect delays) between Binstead Way and Capricorn Drive

Region:

Category:

Date: 
Friday, May 8, 2020 - 16:30 to Saturday, June 6, 2020 - 04:00
planned: 
1
Read more: 

Start date: 8 May 2020

End date: 5 June 2020

Duration: 6:30am – 6pm

Reason: Potholing




closure

Temporary Road Closure - Coolangatta

Streets affected: Lord Street (full road closure local traffic access only) between Musgrave Street and Winston Street

Region:

Category:

Date: 
Friday, May 15, 2020 - 15:00 to Thursday, May 21, 2020 - 04:30
planned: 
1
Read more: 

Start date: 15 May 2020 only

Contingency dates: 18 May 2020,  19 May 2020,  20 May 2020

Duration: 5am – 6:30pm

Reason: To facilitate large concrete pour - 1 day only between above dates




closure

Employer Disclosures for Multi-employer Pension Plans Approved by FASB

The Financial Accounting Standards Board (FASB) recently approved a revised accounting standard intended to provide more information about an employer’s financial obligations to multiemployer pension plans. The revised standard, which the FASB expects to finalize in September 2011, will require… Read More

The post Employer Disclosures for Multi-employer Pension Plans Approved by FASB appeared first on Anders CPAs.




closure

Temporary Road Closure - Stapylton

Streets affected: Quarry Road (half road closure with traffic control – expect delays) between Stapylton Jacobs Well Road and Rossmanns Road

Region:

Category:

Date: 
Tuesday, May 26, 2020 - 04:00 to Wednesday, June 10, 2020 - 16:00
planned: 
1
Read more: 

Also affected: Angel Road

Start date: 25 May 2020

End date: 10 June 2020

Duration: 6pm – 6am

Reason: Road profiling and asphalt works




closure

Temporary Road Closure - Pacific Pines

Streets affected: Pacific Pines Boulevard (lane closure with traffic control – expect delays) between Binstead Way and Capricorn Drive

Region:

Category:

Date: 
Friday, May 8, 2020 - 16:30 to Saturday, June 6, 2020 - 04:00
planned: 
1
Read more: 

Start date: 8 May 2020

End date: 5 June 2020

Duration: 6:30am – 6pm

Reason: Potholing




closure

Temporary Road Closure - Coolangatta

Streets affected: Lord Street (full road closure local traffic access only) between Musgrave Street and Winston Street

Region:

Category:

Date: 
Friday, May 15, 2020 - 15:00 to Thursday, May 21, 2020 - 04:30
planned: 
1
Read more: 

Start date: 15 May 2020 only

Contingency dates: 18 May 2020,  19 May 2020,  20 May 2020

Duration: 5am – 6:30pm

Reason: To facilitate large concrete pour - 1 day only between above dates